Waterford to New Ross Greenway Phase 2 Near Waterford Still Awaiting Opening After Repeated Missed Timelines

Phase 2 Southeast Greenway

Written by Kieran Kelly

January 15, 2026

The Phase 2 section of the Waterford to New Ross Greenway near Waterford remains unopened, despite earlier commitments that this stage of the South East Greenway would be delivered by 2025.

While construction activity has been visible and progress acknowledged in recent months, the absence of a confirmed opening date has prompted renewed concern and frustration among councillors and greenway supporters, who are now seeking clearer answers on delivery timelines.

Commitments Made — But Not Yet Met

Phase 2 at the Waterford end of the route — widely viewed as one of the most anticipated sections — has yet to open, despite expectations that it would be available to users by now.

Recent discussions have seen elected representatives calling for greater transparency, clearer communication, and firmer commitments around when this section will finally be made accessible to the public.

Pressure Growing for Clear Answers

While Greenways Ireland recognises the complexity involved in delivering large-scale infrastructure projects, repeated slippage in publicly stated timelines risks undermining trust in greenway delivery more broadly.

As calls increase for clarity on when Phase 2 will open — and how remaining sections will be progressed — consistent, realistic communication will be critical in restoring confidence.

Greenways Ireland will continue to follow developments closely and report on any confirmed timelines or openings as they are announced.